5                                                            Infrastructure

5.1                                                          Introduction and Consultations

This section discusses characteristics, trends, issues and proposals for action in relation to water supply, drainage, sewage collection and treatment and solid waste disposal.  As part of this exercise a number of meetings and consultations were held with representatives of a number of central government Ministries and agencies.  These consultations are continuing and a list of those carried out to date are shown in Annex 1.

5.2                                                          Existing System Characteristics and Issues

5.2.1                                                     Water Supply

Water for Greater Port of Spain can be obtained from several sources although the bulk comes from the Caroni Arena water treatment works. Other sources that supply water to the area include the Maraval, Hollis, North Oropouche and a number of minor water treatment works and several groundwater sources including El Socorro, Valsayn, Savannah and Four Roads.  There is a reasonably robust water transmission system that feeds water in to Port of Spain and it is believed that there is sufficient conveyance capacity to meet the water demands of the study area for the foreseeable future.

In practice however, water supply to many parts is supplied for a limited number of hours on account of the various source works having inadequate capacity to meet the water demands of the nation as a whole. Several areas, particularly in the upper reaches of the valleys leading into the Northern Range suffer from poor pressures and infrequent service. There are still some communities within the study area that do not have a pipe-borne water supply at present, although it is understood that WASA’s North Water Project will address some of these deficiencies.  Areas that currently have no pipe-borne supply include Upper Gonzales, Upper Perigod Road, Fort George Road and Waterhole Road on Fort George Hill.

In comparison to other parts of the country the Port of Spain area is well served by water storage facilities and there appears to be sufficient overall storage volume to meet the water balancing needs necessary to satisfy diurnal variations in water demand. However, there are some pressure zones that have insufficient storage capacity and studies carried out by Halcrow in 1995/6 suggested that an additional 26Ml of water storage volume should be provided at Maraval, Dundonald, Hololo, St Barbs, Redhill and Morvant with a further 5Ml needed by 2015. Sites for the construction of these facilities should be reserved.

Many of the secondary and tertiary distribution systems within Port of Spain area are hydraulically or structurally inadequate and there is a need to reinforce the network to allow all customers to receive a satisfactory level of service and to reduce leakage levels. WASA has a programme of pipeline works and will install new pipelines as funds become available.

The current North Water Project is addressing some of the deficiencies. Where there is an intention to redevelop an area it would be prudent to take the opportunity to refurbish, replace or reinforce the water mains at the same time.

Although there are some deficiencies with the source capacity and distribution systems these are generally the result of a historical lack of commitment to capital expenditure and maintenance and could be reasonably readily resolved once the necessary funding and resources are made available.

5.2.2                                                     Drainage

(i)                  Flood prone areas

Flood prone areas within the study area fall into three broad categories;

·         Areas where flooding is caused when natural drains first enter the formal drainage system e.g. on entering the paved drains at Bournes Road, Eckel Avenue and where the Maraval River enters the built up area at La Seiva. At these points, water borne debris tends to lodge against structures, causing the channel to be blocked.

·         Locations where the channel gradient abruptly gets to be less steep. This generally occurs at the transition between old land and more recently reclaimed land, such as along the Western Main Road in Cocorite, along Wrightson Road, South Quay, along the Eastern Main Road and notably where the Malick River flows out of the Northern Range onto the plain. The St. Ann’s River noticeably silts up south of South Quay, whereas the concrete channel bottom is quite clean north of South Quay.

·         Locations that are very near to the level of high tide. This is mainly the case near the western end of Independence Square.

(ii)                 Capacity of channels

The capacity of the major channels in the study area is assessed to be about adequate for their hydraulic design load. The St. Ann’s River will require minor upgrading from South Quay going down-river[i]. The flood problems that are experienced are then predominantly a reflection of the fact that debris and silt in the drains decrease their capacity.  This also is felt to apply to a large degree to the smaller local area drains.

(iii)               Development of steep hillsides and upstream catchments

 (Unplanned) development of steep slopes and areas upstream of the formal drainage system contribute to increased flood flows and, more importantly, to increase removal of debris and sediment that blocks channels lower down.

The issue of managing the use of steep slopes in a more responsible manner was the subject of a watershed management study for the Ministry of Agriculture. This study recognised the need for halting the removal of vegetation and other practices that increase flood flows and removal of soil from these slopes.

(iv)               Poor maintenance

In many instances the discharge capacity that is available is far below the design capacity, due to lack of maintenance. The poor maintenance that occurs is the more urgent problem, as the drainage system is not designed to facilitate maintenance. (Difficult access to channels, flat-bottomed channels which encourage sedimentation when flood-flows recede).

(v)                Pump drained areas

An area east of the St. Ann’s River and south of the Eastern Main Road lies below the flood level in the St. Ann’s River. This area drains to a pump station adjacent to the St. Ann’s River, west of Abattoir Road. The efficacy of the system is impaired by the fact that the pumps are not automated (or  manned on a 24 hour basis).  The capacity of the channels approaching the pump-station is less than the pump capacity.  The clogging that frequently occurs in these approach channels further exacerbates this lack of capacity.

The 1983 Port of Spain Drainage Study recommended that this pump-system be upgraded and that two additional pump stations be installed to remove water from the Western End of Charles Street and from Lower Murray Street.  The ground level at these three locations is 2.85 m, 1.5 m and 2.10 m respectively.  (All levels above mean sea level).[ii]. The existing pump station east of the St. Ann’s River serves an area that is only 0.9 m above mean sea level (South Quay east of St. Ann’s River).  High tide design conditions that inform the Port of Spain Drainage Study were taken as 1.6 m above Chart datum.[iii] .  Chart datum, the reference level for tides and nautical charts = the lowest astronomical tide (+ 0 chart datum). Mean Sea Level is + 0.7 m above chart datum.[iv].  The design tide level is then 0.9 m above mean sea level.

5.2.3                                                     Sewage Collection and Treatment

The majority of the study area is served by sewers that drain sewage to the Beetham sewage treatment works (STW) although there is a private sewerage system within the Fairways development in the Maraval valley. The principal unsewered areas are the planned settlements above La Seiva Road in Maraval and Morvant and the largely unplanned settlements within Laventille and Sealots.

Residences in the currently unsewered areas generally have on-plot septic tanks for sewage treatment although the poorer areas utilise pit latrines or cesspits. Unfortunately the majority of these residences are situated on steep slopes where the use of septic tanks, pit latrines and cesspits can create a nuisance and health hazard for downhill residents on account of seepage of partially-treated effluent through the hill faces.

It has been reported that some of the lower-income residents do not even have pit latrines and, presumably, and in these and areas not served by sewers, grey water is generally discharged to open drains, presenting a nuisance to downhill residents as well as odour and mosquito hazards.

5.2.4                                                     Solid Waste Disposal

Solid waste is collected from most parts of the planned urban areas of Greater Port of Spain three times a week. However, there are substantial areas, primarily in the northern hillside developments and Laventille that only have their garbage collected once a week at best, and several difficult to reach parts of these settlements have no access to regular collection services.

There is a common practice of putting garbage bags out into local communal storage bunkers and bins on a daily basis and consequently rubbish may be stockpiled locally for several days before it is collected. During this time vagrants and animals rummage through the rubbish and spread it about, making collection extremely difficult and aggravating the pollution and health hazards associated with storing waste that is awaiting collection.

Another problem that has been identified with the current practice of providing communal waste bins is that they are frequently set on fire, either maliciously or with the intention of alleviating odour problems, which then creates smoke and smell nuisances and also damages the bins.

All solid waste collected in the study area is disposed of to the Beetham waste disposal landfill site on the south of Beetham Highway. The site is poorly designed and inadequately managed. Frequent fires occur on the site, either through spontaneous combustion or, more frequently, through scavengers burning cable insulation in order to salvage copper. At least once a year these fires get out of control and create a very serious air pollution problem for Port of Spain and residents along the east-west corridor.

 

There have been numerous recommendations that the site should be closed down and the Solid Waste Management Company Limited (SWMCoL) have proposed that all waste should be transported to Forres Park for disposal with the Beetham site converted to a recycling and transfer station. It is understood that there is a proposal before the Ministry of the Environment to this effect.

5.2.5                                                     Electricity and Gas

(i)                  Electricity

The Trinidad and Tobago Electricity Commission (T&TEC) has advised that there should be no difficulty meeting the electricity demands for any residential, institutional, commercial or industrial developments that may occur in the Greater Port of Spain area in the foreseeable future. Where a development necessitates a significant reinforcement of the power transmission system to be made, T&TEC would require a capital contribution from the developer but most general in-fill type development can be readily accommodated.

All of the study area is capable of being served by the existing installations although there are some residents who are not currently connected and there is some resistance or inability to pay for service in some of the poorer areas. Historically, T&TEC required a prospective customer to produce land deeds to confirm that they owned the land on which the property was situated. This requirement has now been relaxed at the behest of the Government where the applicant is living on state-owned land.

Much of the high voltage transmission network within the central part of Port of Spain is laid underground and T&TEC is currently embarking on a programme of under-grounding all cables as replacement of cables is required. Currently there are no plans to install major new transmission cables within the Greater Port of Spain area.

(ii)                 Gas

The National Gas Company of Trinidad and Tobago Limited (NGC) has advised that there are two 16”gas lines which run along the Beetham Highway (one either side) with one continuing along Wrightson Road and the other following Dock Road before they terminate at the Port of Spain power station.

An 8”, reducing to 6”, pipeline runs off the 16” pipeline in the docks and follows the T&TEC cooling water outlet channel and the seaward side of the Audrey Jeffers Highway to Cocorite. The only other significant gas line is a 4” main that is connected into the 8”/6” pipe on east bank of the Maraval River. This runs along the river, past Fatima College, around King George V Park, through Jackson Square and then around the inside south-side of the Savannah to the Hilton Hotel. This last pipeline runs under lower pressure (100psi) than the other pipelines (300psi) with the pressure reducing station being situated near to the Highway Bridge over the Maraval River.

NGC currently serves relatively few customers and no domestic users. Main customers in Port of Spain include T&TEC, Peakes Marine and Hilton. They believe that there is a large potential market for using natural gas for air conditioning plants but take-up has been slow on account of the higher capital cost of the air conditioning equipment, despite pay-back periods being only three or so years. NGC believe that the existing pipelines feeding into and around Port of Spain will be adequate to meet any foreseeable demand and they have no plans for constructing additional pipelines.

5.3                                                          Current Proposals and Projects

5.3.1                                                     Water Supply

WASA has recently embarked upon a programme of well drilling that they anticipate will provide between 39 and 77Mld of additional potable water for the country and alleviate some of the current water supply deficiencies.

There had been plans to develop a new run-of-river intake source on one of the rivers in the Northeast of Trinidad, probably on the Matura River, but this proposal appears to have been suspended in favour of drilling wells in the Matura River bed. A desalination facility is currently under construction in the Couva area that is intended to ultimately produce approximately 100Mld of treated water for sale to customers in the Point Lisas Industrial Area.

However this plant will not permit additional water to be released from existing sources for use by other consumers as the water demand in the Point Lisas area is anticipated to rise by 100Mld over the next 5-10 years.

Once the well developments are on-line there should be approximately 5-10% more water available for consumers outside of the Point Lisas Industrial Estate.

5.3.2                                                     Drainage

MOW Drainage Division basically deals with drainage but it is understood that there are no major works planned to address the major issues. The following minor works are however programmed:

·         La Seiva Bridge Reconstruction (1997/8 design);

·         Beetham Estate Drains (John John area studies 1999 implement up to 2006);

·         Lady Hochoy Drain (Cocorite walling works);

·         Malick River (upstream of 7th Av. to Lady Young) Studies 1997 implement walling works TT$ 50,000;

·         Outside of the plan area of Greater Port of Spain, but impacting on the Malick River, there are plans for works on the Mon Repos Drain (Never Dirty).

·         Maraval river repairs (TT$ 90,000).

·         Local Area Drainage along sewer traces.

The Port of Spain City Corporation has embarked on a programme of leasing the sewer traces to the adjacent owners, to relieve itself of the maintenance responsibility that these traces present. However, the terms and conditions of these lease arrangements warrant careful attention to ensure that the new use of these sections of land does not impact negatively on surface drainage.

(i)                  Policy Framework

The responsibility for implementing and maintaining the drainage system in the Greater Port of Spain area is spread over various agencies, which lack a common framework or clear and rational division of responsibilities.

These are:

·         Drainage Division (M.o.W.)

·         P.o.S. City Council

·         San Juan/Laventille Regional Corporation

·         Diego Martin Regional Corporation

·         Ministry of Agriculture’s Watershed Management programme.

·         The Land Settlements Agency (Ministry of Housing & Settlements) who are responsible for squatter regularization.

(ii)                 Drainage Policy and Objectives

The Drainage Division has a stated policy to conserve the existing runoff regime. Developers are required, as an approval condition, to estimate the pre-development response to a (20 year) design storm. The post-development situation must then show how to achieve a response to the same design storm that does not exceed the pre-development response.

This seems to have potential for problems as over time there will be nothing to stop the owner either failing to maintain the on-plot storage or paving it over.

It may be preferable to request developers to contribute into a fund at a rate depending upon the size of the development and the area that is paved/covered which can then be used for provision for flood alleviation ponds or similar facility to serve groups of properties.

The Master Plan should incorporate a drainage structure plan for gradual completion/infilling by developers as new sites are constructed. This structure plan should seek to:

·         Identify areas at risk of flooding and capable of being used to store flood water – these areas should not be developed unless temp storage capacity afforded by them can be provided elsewhere.

·         Identify areas that need to be protected from erosion (eroding gullies).  In protecting these areas by slowing downs flood flows, substantial detention storage can also be achieved

·         Identify areas that are difficult to drain and avoid passing upstream water through these areas.

·         Identify areas inadequately drained but capable of being drained if pipes, culverts or channels are upgraded.

·         Ensure that ultimately the fully developed area will not respond less favourably to the design storm than obtained in the pre-development situation.

(iii)               Detention Pond Design

From a perspective of safety and aesthetics it is recommended that ponds be designed for level fluctuations that are designed to not exceed 1 to at most 1.5 m.

To minimise clogging the outflow it is recommended that outflow is controlled by a VEE-shaped notch with sides at 45° to the vertical. Flows should approach the outflow notch through a trash rack that has an available flow-through surface not less than five times the cross-sectional area of the outflow control.[v].

The trash rack should slope upwards at an angle to a horizontal grille where debris can be collected, that can support maintenance personnel and from which debris can be easily raked into a wheeled debris container. The metal bars that comprise the Grille are to be oriented to facilitate raking debris from the grille.

It is proposed to design detention ponds to so that the peak-flow in response to the design storm is 30 litres/second/Ha. of drainage area. Both the St. Ann’s and Maraval Rivers have a capacity/area ratio of 30 L/S/Ha. [vi] 

Together with the desire to avoid using small outflow openings that clog easily, the proposed permissible water-level fluctuation indicates that ponds should serve areas of 40 to 100 Ha.

It is recommended that the area that is inundated frequently be landscaped as a wetland or a permanent water-pond, linked to environmental and conservation programmes. Permanent water ponds need to be well aerated. Aeration may be achieved if the pond serves a perennial stream by guiding the inflow to cascade over adequately dimensioned broad-crested weirs or by operating a waterspout-pump.  An outflow control should also be installed to permit complete evacuation of the facility.  Due attention must be given to facilitating removal of sediment.

(iv)                Check Dam Design/Development

Check dams are (small) dams placed in steep gullies to break the speed of water flowing down these gullies in order to break the destructive force of fast flowing water. Checkdams serve to halt further erosion of gullies and to promote deposition of sediment on the upstream side of the Gullies. If the checkdams are effective they will eventually transform the gullies in which they are installed to a series of steps.

On steep slopes the risk of inundation does not exist. The major concerns with respect to surface runoff centre on:

·         Avoiding erosion and destruction of infrastructure by the forces of swiftly flowing water.

·         Avoiding flooding in the downstream reaches due to accelerated runoff.

Checkdams are effective in maintaining low-flow velocities as well as temporarily storing significant volumes of water. Checkdams can also be installed at a fraction of the cost that would be required for installing similar discharge and storage capacity in traditional concrete structures.

 

Checkdams may be installed as a pile of boulders placed across a gully or as a palisade of trees or stakes that will readily catch and grow to healthy trees in the ambient environment.  Trees and boulders may be combined as a line of boulders with a palisade of stakes in a line touching the upstream side of the boulders. Checkdams are to be installed, starting at the upstream limit of a catchment, working in a downstream direction.

Checkdams cannot be installed in one construction operation, but will require ongoing maintenance and adjustment over a long period.  The overall costs are however significantly lower than costs for a drain installation of comparable capacity in concrete.  In fact, the costs that are associated with traditional construction are basically prohibitive so that in steep terrain checkdams are the only realistic option for managing surface runoff in low cost housing development.

Checkdams will form a barrier for water-borne debris and are consequently absolutely unsuited for an environment where solid waste is not ef