Urban Development Corporation of Trinidad and Tobago Ltd Ministry of Housing and Settlements Trinidad & Tobago Local Area Plan Tranche 1 Studies GREATER PORT OF SPAIN LOCAL AREA PLAN GREATER PORT OF SPAIN MASTER PLAN (DRAFT) Technical Report |
|
DECEMBER 2000 HALCROW GROUP (TRINIDAD & TOBAGO) LTD. In
association with THE JOINT CONSULTATIVE COUNCIL FOR THE CONSTRUCTION INDUSTRY |
Halcrow Group (Trinidad & Tobago) Ltd has prepared
this report in accordance with the instructions of their client, The Urban
Development Corporation of Trinidad and Tobago Ltd., for their sole and specific
use. Any other persons who use any
information contained herein do so at their own risk. © Halcrow Group Limited
2000
Halcrow
Group (Trinidad & Tobago) Ltd.
133 Sixth
Street, Barataria
Tel: 674-7741
/ 674-2911
Fax: 675-1995
Halcrow@tstt.net.tt
Contents
PART
ONE
1
1
Introduction
1
1.1 Background
1
1.2 Current Programme and Objectives 1
1.3 Approach and Method 2
1.4 Format of this Report
5
PART
TWO
7
2 Context
8
2.1 Study Area
8
2.2 Land Use Overview - Opportunities and Pressures
9
3 Socio-Economic
Background
13
3.1 Population and Households
13
3.2 Housing
24
3.3 Employment And Economic Activity 35
3.4 Summary and Conclusions
48
4 Transport
52
4.1 Introduction
52
4.2 Existing System Characteristics 53
4.3 Current Transportation Schemes and Proposals
60
4.4 Priorities for Action
65
4.5 Summary
70
5 Infrastructure
73
5.1 Introduction and Consultations
73
5.2 Existing System Characteristics and Issues 73
5.3 Current Proposals and Projects 79
5.4 Priorities for Action
85
5.5 Summary
96
PART
THREE
103
6 Downtown/Uptown/Tranquility/Newtown 104
6.1 Characteristics and Issues
104
6.2 Proposals for Action 113
6.3 Implementation and Phasing
118
7 Woodbrook
123
7.1 Characteristics and Issues
123
7.2 Proposals for Action 127
7.3 Implementation And Phasing
132
8 St. Clair/
Federation Park/ Ellerslie Park
136
8.1 Characteristics and Issues
136
8.2 Proposals for Action 138
8.3 Implementation And Phasing
141
9 Savannah
145
9.1 Characteristics and Issues
145
9.2 Proposals for Action 150
9.3 Implementation and Phasing
152
10 St.
James
156
10.1 Characteristics and Issues
156
10.2 Proposals for Action 159
10.3 Implementation and Phasing
159
11 Northern
Hillside Communities
161
11.1 Characteristics and Issues
161
11.2 Proposals for Action 179
11.3 Implementation and Phasing
181
12 East Port of Spain
183
12.1 Characteristics and Issues
183
12.2 Proposals for Action 192
12.1 Implementation and Phasing
195
PART
FOUR
200
13 The Way Forward
200
13.1 Public Consultation – Local Area Plans 200
13.2 Implementation Mechanisms
201
This
document represents the Interim Report for the Greater Port of Spain area.
This part of the report consists of the following:
·
Background
·
Current
Programme and Objectives
·
Approach
and Method; and
·
Format
of the Report
The
Halcrow Group together with a local team of consultants and specialists was
appointed by the Government of Trinidad and Tobago in February 1999 to provide
planning and development advice at national and local scales. The initial work concentrated on preparing
a National Conceptual Development Plan (NCDP) which was to be used as a framework
for a number of Local Area Concept Plans, which have all been completed.
The
key stages of this work incorporated:
·
A Land Use Strategy, including a planning justification of the Balanced
Growth approach which has been adopted to guide national development
·
Sectoral Overview and Policy Guidelines, including an analysis of industrial
and employment characteristics and other key sectors impacting growth potential
·
The National Conceptual Development Plan Proposals, including a Local Area
Concept Plan Framework, in text and illustrative plan form.
The
current programme represents the first tranche of Phase 2 (Local Area Planning)
for physical planning in Trinidad and Tobago.
It builds on and refines the earlier work carried out for the NCDP
and has been undertaken in joint venture with a wide range of local experts
and companies.
The main purpose of the current programme is to
prepare local plans for three priority urban areas, based on their respective
concept plans completed under the NCDP studies. The first of these local plans is for Port of Spain, which is the
subject of this draft report.
The
objectives of these plans are:
·
To provide the basis for development control
·
To identify priority infrastructure development projects
·
To increase developer interest
·
To facilitate housing land delivery for low income households
·
To improve consultations and discussions between concerned agencies and
the public
·
To enhance and protect the local physical and human environment
This
document represents the Interim Report for the Greater Port of Spain area. Following submission and review it will be
subject to further public consultation, prior to refinement and completion
in Draft and Final Master form. More
detailed Action Area Plans are designed to follow in later tranches.
The
Local Area Plans are based on the Concept Plans, which were drawn up from
readily available information, discussions with key stakeholders, identification
of on-going projects and limited fieldwork. The Concept Plans were designed to:
·
Illustrate
overall spatial strategy
·
Identify
key planning constraints
·
Illustrate
principal development opportunities.
·
The aim of the current study is to
transform these Local Area Concept Plans into more detailed Local Area Plans.
The
scope of Local Area Plan work is as follows:
·
Confirm
critical assumptions made in the Concept Plans, including current policies,
programmes and commitments
·
Prepare
a robust Master Plan for the development of each area, incorporating a land
use strategy and policies for key elements, which address significant environmental
impacts
·
Identify
urban design briefs and planning guidelines for selected areas including for
example, low, medium and high density housing areas, the central area, industrial
areas and open space/recreation.
·
Formulate
priority action proposals needed to instigate development, including responsibilities
as between the public and private sectors, identification of priority infrastructure
projects, overall cost estimates, phasing and institutional requirements.
The
method used followed a bottom-up/top-down approach to issue identification
and resolution. Greater Port of Spain consists of a number of more or less
discrete neighbourhoods and communities which were identified in the Concept
Plan and previous studies. These neighbourhoods have been grouped together
where common land use attributes exist so that issues and opportunities could
be explored on a local scale.
This
bottom-up approach has been merged with the top-down approach identified at
Concept Plan stage to ensure that local and area-wide priorities are clearly
identified. Using a local area approach
will also help discussion of issues during the consultation and participation
phase of this study.
Some Limitations
The
time frame for this work precluded any further detailed analyses or data collection. However the nature of this exercise in relation
to the process of adapting the existing national planning process (the NPDP)
indicated that the focus of future work should be more flexible and action–oriented
in terms of priorities for instigating development.
Nevertheless
it is normally the case that physical planning actions are only one in a series
of integrated actions that will be required to optimise impacts and in some
areas, these are not the most critical. Where
this is the case the complementary actions have been identified and some options
for implementation mechanisms have been identified.
Consultation Process
A major feature has been the conduct of a range of meetings and consultations
with Government Ministries, agencies and authorities, the private sector and
non-governmental organisations (NGOs). Following submission of this draft report, it is intended to hold
a programme of public consultation, including public meetings in each local
area, so that the needs and aspirations of existing communities are fully
taken into account.
Outputs
An
analysis of the local and area-wide opportunities, action areas and implementation
mechanisms forms the basis of the strategies and proposals for Greater Port
of Spain over the next 20 year period.
The
principal outputs consist of:
·
A
Master Plan showing broad land uses, development strategies and principal
highways
·
A
Transportation Network Plan
·
An
Infrastructure Plan, showing trunk networks and facilities
·
A
Development Phasing Strategy, for time horizons of 5, 10 and 20 years
·
A
Concise Report, including data and analysis, policies and proposals and identifying
a ‘short list’ of areas or topics where priority actions are likely to be
required.
Next Steps
As
part of the next phase of work the consultation process for the Plan outlined
above will commence and inform the identification and refinement of priority
action proposals, including the identification of responsibilities for implementation
as between public, community and private sector agencies. Broad cost estimates for public sector infrastructure
projects, phasing and institutional requirements will also be identified.
This
Interim Report is presented in four parts:
Part One, which
comprises this Introduction (Section 1), and which is preceded by the
Executive Summary;
Part Two,
which describes the Context of the current work and includes sections on
·
Study
Area and Land Use (Section 2)
·
Socio-Economic
Background (Section 3)
·
Transport,
and (Section 4)
·
Infrastructure
(Section 5);
Part Three,
which identifies and discusses the policies and proposals for action in selected
key areas of Greater Port of Spain as follows:
·
Downtown/Uptown
(Section 6)
·
Woodbrook
(Section 7)
·
St
Clair/ Federation Park/ Ellerslie Park (Section 8)
·
Savannah
(Section 9)
·
St
James (Section 10)
·
Northern
Hillside Communities (Section 11) and
·
East
Port of Spain (Section 12).
Part Four,
which outlines proposals for the Public Consultation process which is to follow
this stage of the work (Section 13).